Demolition of the Red House
Dear Resident
As you are aware Demolition work has progressed with the initial site set-up and soft strip of all internal fittings and timber work.
As of Monday structural demolition will start by Demolition Excavator working on a North-South axis and continue through the week. Redundant masonry will be stock piled on site for removal in eight-wheeled lorries later in the week. The contractor is looking to be completed and clear from site by Friday November 5th.
There will be minimal noise disturbance, only the noise of the Excavator running and brick rubble being loaded into lorries. Water will be applied throughout the process to suppress any dust arisings.
It is important that this work is completed as quickly as possible as the cliffs at this point had almost reached a point where safe demolition could not be achieved.
Aldringham-cum-Thorpe Parish Council