Sizewell C
Current discharge applications:
- DC/24/4508/DRR – Requirement 39, Rail Noise Mitigation Plan
- DC/25/2212/DRR42 – Requirement 33, Buildings, structures and landscape, Northern Park and Ride
- DC/25/2066/DRR – Requirement 36, Highway Landscape Works, Friday Street Roundabout
- DC/25/2274/DRR42 – Requirement 33, Buildings, structures and landscape, Southern Park and Ride
- DC/25/2591/CCC – SCC Consultation, Requirement 23, Highway Works, Leiston Drain Bridleway Bridge
- DC/25/2165/DRR28 – Requirement 36, Highway Landscape Works, Two Village Bypass
- DC/25/2580/DRR – Requirement 5, Surface and Foul Water Drainage, Southern Park and Ride
- DC/25/2790/DRR42 – Requirement 30, Accommodation Campus: Building and Structures, Construction Parameter Zones CA1 and CA3
- DC/25/2993/DRR – Requirement 36, Highway Landscape Works, Sizewell Link Road
- DC/25/3054/DRR – Requirement 5, Surface and Foul Water Drainage, MDS Phase 8
- DC/25/3090/DRR42 – Requirement 19, MDS Marine infrastructure, Temporary Hard Coastal Defence Feature (Work No. 1A(n)) and Temporary Marine Bulk Import Facility (Work No. 1A(aa))
- DC/25/3244/DRR28 – Requirement 2, Bespoke Mitigation Plan, Rail Works September 2025 – February 2026
- DC/25/3245/DRR28 – Requirement 2, Bespoke Mitigation Plan, Temporary Construction Area Works September 2025 – April 2028
- DC/25/3246/DRR28 – Requirement 2, Bespoke Mitigation Plan, Yoxford Roundabout October 2025 – March 2026
- DC/25/3344/CCC – SCC Consultation, Requirement 35, Highway Works, Sizewell Link Road
- DC/25/3345/CCC – SCC Consultation, Requirement 10, Public Rights of Way Implementation Plan, Sizewell Link Road
- DC/25/3346/CCC – SCC Consultation, Requirement 35, Highway Works, A1094/B1069 Junction South of Knodishall
- DC/25/3347/CCC – SCC Consultation, Requirement 35, Highway Works, A12/B1119 Junction at Saxmundham
Recently discharged applications:
- DC/25/1991/DRR – Requirement 5, Surface and Foul Water Drainage, Various Main Development Site Works (Phase 7)
- DC/25/2575/DRR28 – Requirement 2, Bespoke Mitigation Plan, Yoxford Roundabout
- DC/25/2515/DRR28 – Requirement 2, Bespoke Mitigation Plan, Two Village Bypass
- DC/25/2516/DRR28 – Requirement 2, Bespoke Mitigation Plan, Ancillary Construction Area Works
- DC/25/2644/DRR28 – Requirement 2, Bespoke Mitigation Plan, Sizewell Link Road
- DC/25/2275/DRR – Requirement 5, Surface and Foul Water Drainage (Operational), Northern Park and Ride
- DC/25/2606/DRR42 – Requirement 32, Site Clearance, Green Rail Route
- DC/25/2544/DRR – Requirement 20, SSSI Crossing, Temporary bailey bridge
Forums update:
- ESC recently attended the Northern Transport Forum (held 6August 2025). Next forum will be the Southern Transport Forum to be held on 3 September 2025.
- Community Forums - Sizewell C
Works Tracker:
- Works are ongoing across the Main Development Site and Associated Development Sites. Works to build the foundations of the water desalination plant and concrete batching plant on the Temporary Construction Area have begun, and preparations for the installation of the first bridge over the Site of Special Scientific Interest continue. The first section of the plastic cut-off wall on the perimeter of the Main Construction Area has been installed - once complete, the wall will enable dewatering and bulk excavation. Earthworks are progressing on the Ancillary Construction Area, with deliveries of ballast and pre-assembled straight track sections taken in preparation for the construction of the railhead. Construction of the northern section of the temporary sea defence has begun, with the first sheet piles being installed. Marine surveys are taking place in the marine harbour in preparation for construction of the Beach Landing Facility and Marine Bulk Import Facility, expected to begin late in 2025. Works on the new junction of Lover’s Lane and Abbey Road have started as part of realignment works to enable the installation of a new level crossing for the Green Rail Route, whilst preparations at the site of the plaza roundabout continue. Vegetation removal at the Friday Street Roundabout site is complete, and all site accesses along the Two Village Bypass have been established in preparation for construction. Preparations for the construction of Sizewell Link Road, including the setting up of compounds, establishing haul roads, and moving equipment, continue. Construction of Yoxford Roundabout continues, with a programmed completion date of mid-2026. Site preparation works continue at the Northern and Southern Park and Ride sites, and construction of the roundabout next to the A12 and Willow Marsh Lane at the Northern Park and Ride has begun. The Freight Management Facility at Orwell Logistics Park is fully operational. The new compound at Leiston Airfield, which will allow the teams delivering rail improvements to move from the Buckleswood Road compound, is now complete.
- The project has an online works tracker providing real time updates on works across all project sites, and the option to subscribe for parish or site specific works updates - Sizewell C Works Tracker - Track SZC Projects & Get Alerts for New Activities
SPR
SPR Discharges lodged with ESC (relating to EA1N and EA2):·
2x R21(2) Ecological Management Plan and R26(1) Onshore Preparation Works Management Plan (EA1N and EA2) – footpath creation works.·
2x R21(2) Ecological Management Plan, R22(1) Code of Construction Practice, R26(1) Onshore Preparation Works Management Plan – (EA1N and EA2) – cable enabling works.
SPR EA1N and EA2 – other updates:·
Application DC/25/2037/FUL (HDD works under Hundred River) – Determination deadline 26th September 2025.·
Works formally commenced on the substation haul road phase at the end of July 2025.
Archaeological mitigation (pre-commencement) works on site are ongoing (i.e. geophysical surveys, trial trenching, archaeological monitoring) between Friston substation working eastwards along the onshore cable route to the landfall site north of Thorpeness – due to end January 2026.
You can monitor current and future planned activity using the ‘East Anglia TWO And ONE North Project Activity’ tracker https://www.scottishpowerrenewables.com/pages/east_anglia_two_and_one_north_activity.aspx
Sea Link - NGET
- Application currently in pre-examination phase – ESC awaiting draft examination timetable being published by PINS.
- Up to date information available on the Planning Inspectorate’s websiteSea Link - Project information
- ESC submitted a response to the Ofgem Early Construction Funding Consultation in August 2025 https://www.ofgem.gov.uk/consultation/sealink-early-construction-funding-consultation
LionLink Multi-purpose Interconnector – NGV
- Engagement on the project continues - the next round of formal consultation (Statutory Consultation and Preliminary Environmental Information Report – PEIR published for comment) - expected Q1 2026.
- DCO submission to PINS expected in late 2026.
- LionLink About | National Grid Group
Grahame Stuteley BSc (Hons) MSc MRTPI | Principal Planner - Energy ProjectsEast Suffolk Council